Generator Exchange at Pumping Station, Hampshire
We recently completed a generator exchange at a pumping station in Hampshire, removing the retiring generator and replacing it with a new one.
Published 10/02/2026
In December 2025, A R Banks Ltd was appointed as Recovery and Salvage Contractor for the beachside recovery of multiple 40-foot shipping containers lost during the Baltic Klipper incident. The appointment was made by Marine Salvage Consultants as part of a wider multi-agency response involving local authorities and key statutory stakeholders.
The incident resulted in container shells and fragmented sections being dispersed along a substantial stretch of the West Sussex coastline, from Selsey to Bognor Regis.
This was a fast-moving and highly dynamic recovery operation undertaken in a live coastal environment. The recovery works needed to be delivered swiftly, while maintaining strict controls around safety, environmental protection, public interface and reinstatement.
The operation required the coordinated mobilisation and demobilisation of multiple work fronts, with plant, supervision, lifting teams and groundworks crews continually redeployed between locations as recovery priorities shifted. Each site effectively functioned as a short-duration project in its own right, requiring rapid setup, execution and reinstatement before assets were moved on to the next location.
Scope of Works
The works were subject to tidal windows, weather exposure, restricted access points, public interface considerations and environmentally sensitive shoreline conditions.
Given these factors, environmental protection formed a key element of the works. Later recovery phases were delivered using low-ground-pressure plant fitted with bio-oils, reducing the risk of contamination and ground disturbance.
Upon authorisation to commence, A R Banks fully mobilised recovery assets, personnel, supervision and site infrastructure within hours. We developed all methodologies, risk assessments and lifting plans swiftly and ensured they were formally reviewed and approved by all stakeholders prior to works commencing.
The operation was delivered through a phased, multi-site approach, allowing recovery works to progress simultaneously across the coastline while maintaining programme flexibility.
Two 25-tonne tracked excavators were deployed as primary recovery machines, undertaking shoreline lifting operations and relocating containers to suitable handover locations. From there, containers were transferred onto specialist road transport and escorted to a designated central compound.
At the compound, a 100-tonne mobile crane was utilised to off-load containers from transport and position them safely for future deconstruction activities.
Enabling Works & Reinstatement
Ahead of all lifting and recovery operations, dedicated groundworks teams carried out enabling works to facilitate safe and efficient recovery. These works included:
Once recovery operations at each location were completed, our teams undertook full reinstatement works before demobilising and redeploying to the next site. This approach minimised disruption to the public and ensured that all areas were returned to their original condition, or better.
Plant & Equipment Deployed
The recovery operation utilised a varied and flexible fleet, including:
All lifting activities were planned and executed in full accordance with BS 7121.
The works were delivered with no reportable incidents, reflecting robust planning, experienced supervision and close coordination throughout the operation.
In January, our teams were subsequently assigned to support further container recovery operations following the Lombok Strait incident, continuing our involvement in time-critical marine salvage and coastal recovery works.
If you’re in need of recovery and salvage solutions, please get in touch with our friendly and experienced team.